Signal Path Compensation (SPC) can be run at any time. The best times to run SPC are:
- After the oscilloscope has been powered on and has warmed up for 20 minutes or more.
- If the temperature has changed more than 5 degrees C since the last SPC was run.
- Prior to making a critical measurement.